Search This Blog

Thursday, September 24, 2015

Installation, continued...

Now that the posts are all in place for phase two of our solar array, we are ready for concrete!  The truck came yesterday, and the crew was busy pumping concrete, making sure that the posts stayed level as the concrete rushed into the holes.  After one truckload was poured, all but three post holes were filled, so we had another smaller load of concrete come down to the site today to fill the remaining holes.  With all of the posts now set in concrete, the crew is setting up the mounting hardware, and beginning to mount the panels!  We hope to have all the panels mounted by the end of the day tomorrow (Friday).  Then we can begin the work of wiring the panels to the inverter, and then into our electrical system.

The posts are set, leveled, and ready for panels!
The posts are secured in 8 feet of concrete.  These puppies aren't going anywhere...

The first panel of the second phase is mounted!

No comments:

Post a Comment