Search This Blog

Monday, April 18, 2011

Milestone reached!

A milestone is a scheduled event signifying the completion of a major deliverable.  It is a flag in the work plan to signify a portion of work has been completed.
Today we reached a milestone event in the Guam Transmitter Upgrade Project.
The building and transmitter hall modifications were completed (major deliverable) to the point where we were able to bring the new transmitters from their storage containers located near the antenna field into the transmitter building.
The physical move of the 14,000lb (each) transmitter required the assistance of a crane and flatbed.  This is a high risk event because of the potential danger posed to equipment and personnel.   Any mishap could stop or change the project timeline.

  Pulling TX6 out of its 10 month container home.


Placing TX6 on Flat bed



We are happy to report the move was successful!  Thank you for joining us in prayer to keep rain away and maintain personnel and equipment safety.

 Tonight the transmitters are temporarily staged in the shop and transmitter hall and will be rolled in to their permanent operational location in the transmitter hall in the next few days



This milestone event was a major accomplishment as it marks the start of “phase 3” of the project where we will be connecting and testing the transmitters.






 Update: 20 April 2011

The Transmitters were rolled into place on Tuesday April 19th.

Here are a few more pictures: