Monday, October 25, 2010

Getting the Thumbs Up




Things are progressing well with getting TX 1 pieced back together and up and running. All the wiring has been completed; it received a good cleaning, and this past week the steam and condensate pipes were connected to the radiator. The unit is now being tested and while there are a few things that have to be tweaked, the first analysis has gone well. Soon attention will be turned to TX 2 which also needs it's cooling radiator moved outside. While TX 2 itself will not be moved, the radiator transition means that TX 2 will have to be taken down for at least one night. However before this happens, we need to give our listeners ample warning ahead of time of the change so they will know their program will not be aired that day.

As you are aware, there has been much work done to move the cooling radiators outside so that the new transmitters can be in an air-conditioned environment. Those air-conditioners are on their way and should be here within the next two weeks. Planning meetings are being held to plan all the steps needed to install the air-conditioners in a timely manner.

Brief news: --A new phone system has been put into place with each team member receiving their own phone and extension.. . thanks to the hard work of Cassius Smith.
--November brings a new broadcast season (B10) so preparations are being made for frequency and program changes.

1 comment:

  1. Thanks for the updates. I love reading the reports on your progress.

    ReplyDelete